Work Continues… Work on our Lime Grove development in Seaforth, Sefton continues ahead of schedule, with the roofs on block A, and internal fit-out starting this week. Brickwork on block B will be completed shortly, with the foundations in on block C and brickwork progressing – the project is due to be completed by April 2016.…